Installation
Installation sequence
- Ensure the substrate is dry, free from projections, irregularities and gaps.
- Lay vapour control layer.
- Lay ROOFMATE™ RL-X boards broken bond with the long edges at an angle of 45º - 90º to the crowns of the decking. Tightly join all boards to form a continuous layer over the roof.
- Secure each board to the decking with three fixings, evenly distributed and installed in accordance with the fixing manufacturer’s instructions. Half boards or smaller require only two fixings.
- Cut ROOFMATE RL-X boards to fit against upstands and penetrations with a saw or sharp knife.
- Cover ROOFMATE RL-X boards with a separating layer (if specified) followed by the waterproofing membrane and secure it as soon as possible.
- Remove and store unused boards overnight.
Key points
- Where persistent impact is likely, protect ROOFMATE RL-X boards with a suitable underlay board or protective slabs.
- When hot air welding seams in the waterproof membrane take care not to damage ROOFMATE RL-X insulation by excessive heat.
- When solvent welding seams, do not let solvent come into direct contact with the ROOFMATE RL-X boards.
|
|