Installation
Installation sequence
- Fit an isolation strip around the perimeter. Lay the layer of FLOORMATE™ boards across the whole floor.
- Lay QUASH™ EF. At perimeters turn QUASH EF at least 100mm up the wall.
- Form butt joints between adjacent runs of QUASH EF. Ensure that there are no gaps.
- Seal with self adhesive acoustic tape tape. Alternatively lay QUASH EF with 100mm laps taped to limit movement during screeding and to prevent screed from creeping between the layers.
- Apply the screed. If a free flowing screed is used then overlap QUASH EF with polyethylene sheet (500 gauge) taping all joints and lapping it up around the perimeter by 150mm.
- When lining the wall, turn QUASH EF down under the skirting. Trim off excess.
- Fit floor finish
- Install the suspended ceiling.
Handling and storage
QUASH EF is supplied in polyethylene wrapped rolls. Store the rolls on end in a dry place out of direct sunlight. Although the rolls are not heavy, weighing less than 20kg, they are bulky: take care when handling.